Duke Energy Central Corridor Pipeline update

(October 18, 2021 - Blue Ash)


Duke Energy has the following construction updates regarding the Central Corridor Pipeline project:

  • Glendale Milford will likely reopen to traffic by the second week of November
  • Pipeline on Reed Hartman Highway north of Creek Road should be completed and restored by the end of this week
  • Late this week, the sidewalk along the east side of Reed Hartman Highway between Ilmenau Way and Osborne Blvd. will begin being restored
  • Ethicon restoration to take place this week
  • Roundabout pavement still requires final restoration which will take place once paving crews become available
  • Summit Park split rail fence has been installed
  • Summit Park valve station concrete decorative walls will likely be completed sometime after Thanksgiving

These updates are weather permitting.  Thank you for your continued patience as this work is completed.